7 North-South Expressway projects will be 'finished' half a year early
Project news
28/08/2024
Specifically, the representative of the Ministry of Transport said that through the inspection and review of the progress of relevant units, it was shown that as of August 20, 2024, the construction site at 12 North-South Expressway projects in the 2021-2025 phase being implemented had been handed over by localities 99.8%. Specifically, localities have handed over about 719.49 out of a total of 721.25km of land that needs to be cleared for the construction of 12 North-South Expressway projects in phase 2.
“Compared to the progress required by the Government, this work is being carried out slowly by some localities. Typically, in Ha Tinh province, there are still 11/14 locations; Quang Tri has 02/03 locations; Binh Dinh has 6/61 locations; Phu Yen has 73/82 locations; Khanh Hoa has 17/20 locations; Hau Giang still has 5/7 locations... The locations that are slow to be relocated and cleared are mainly high-voltage power lines," a representative of the Ministry of Transport informed.
![]() |
Seven out of 12 North-South expressway projects will be completed half a year ahead of schedule. Photo of the Bung - Van Ninh expressway construction site. |
However, assessing the construction work at the site and the progress of the projects, the representative of the Ministry of Transport said that, based on the synthesis of reports from the Project Management Boards (PMUs - representing the investor) on the progress and construction output, as of August 20, there were 7 component projects that completed the main route on April 30, 2025 - half a year ahead of schedule. These 7 expressway projects include: Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Vung Ang - Bung, Bung - Van Ninh, Van Ninh - Cam Lo, Chi Thanh - Van Phong, Van Phong - Nha Trang.
Referring to the specific output of the above projects, the representative of the Ministry of Transport said that the output to date is about 47,208 billion VND - reaching 48.9% of the contract value. Of which, a number of projects have been implemented to meet the required progress and have high output reaching over 52% (total output of 12 projects) compared to the contract value, including: Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Vung Ang - Bung, Bung - Van Ninh, Van Ninh - Cam Lo, Chi Thanh - Van Phong, Van Phong - Nha Trang; the two Vung Ang - Bung projects alone reached 62.8%, the Van Phong - Nha Trang project reached 67% of the contract value.
To open the North-South expressway from Lang Son to Ca Mau and complete the target of 3,000 km of expressway by 2025 according to the National Assembly Resolution, on January 1, 2023, 12 component expressway projects of phase 2 (2021-2025) were "pressed" by the leaders of the Government and relevant ministries and branches. The 12 projects have a total length of about 700 km, passing through 12 provinces and cities, including the following provinces and cities: Ha Tinh, Quang Tri, Quang Binh, Quang Ngai, Binh Dinh, Can Tho, Ca Mau. The project is invested in a phased scale with a roadbed width of 17 m, 4 lanes, and a design speed of 80 to 100 km/h.
12 expressway projects are scheduled to basically complete the main route in 2025. To achieve this goal, at the groundbreaking ceremony of the 12 projects, the Prime Minister requested the Ministry of Transport to direct project management boards, supervision consultants and contractors to work with the highest sense of responsibility, mobilize human resources and modern machinery to carry out the project with the spirit of "overcoming the sun and rain", working "3 shifts, 4 teams" to speed up progress; along with that, the Prime Minister also requested that construction be carried out quickly but must ensure safety, quality, and compliance with construction procedures, and not allow corruption or negativity to occur.
Get the latest information !
Receive the latest market information sent via email week
Featured news
Articles on the same topic
Sở Xây dựng Khánh Hòa và các đơn vị liên quan đang tiếp tục hoàn thiện kế hoạch chi tiết, để tổ chức hội nghị lấy ý kiến người dân về các khu tái định cư phục vụ dự án đường sắt tốc độ cao Bắc - Nam.
14.08.2025
UBND tỉnh Khánh Hòa vừa quyết định giao Công ty CP Đầu tư Xây dựng và Phát triển đô thị Minh Ngọc liên danh với Công ty CP Xây dựng và Ứng dụng Công nghệ Delta V làm chủ đầu tư dự án nhà ở xã hội tại phường Nha Trang với tổng vốn đầu tư hơn 2.200 tỷ đồng.
14.08.2025
Liên danh có công ty thành viên thuộc Sun Group sắp khởi công khu đô thị hỗn hợp hơn 17.000 tỷ đồng tại Nam Nha Trang, quy mô 226 ha, dự kiến cung cấp hơn 5.700 căn nhà ở.
09.08.2025
Tỉnh Khánh Hòa được Thủ tướng giao xây dựng hơn 10.000 căn nhà ở xã hội trong giai đoạn 2025 - 2030, nhưng tỉnh dự kiến hoàn thành hơn 40.000 căn đến năm 2030.
01.08.2025
Liên danh của Vinhomes bắt đầu triển khai phân khu đầu tiên hơn 2.000 ha thuộc khu đô thị mới Cam Lâm từ 2026, vận hành từ quý IV/2028.
24.07.2025
Thủ tướng đề nghị tập đoàn Nhật Bản cùng đối tác Việt Nam nhanh chóng triển khai dự án Thành phố thông minh Bắc Hà Nội 4,2 tỷ USD.
23.07.2025
Ngày 18/7, UBND tỉnh Khánh Hòa cho biết, địa phương đã đăng ký với Bộ Xây dựng và đang chuẩn bị khởi công 4 dự án quy mô lớn, với vốn đầu tư hàng nghìn tỷ đồng nhằm chào mừng kỷ niệm 80 năm Quốc khánh Nước Cộng hòa xã hội chủ nghĩa Việt Nam (2/9/1945 – 2/9/2025) vào tháng 9 tới.
18.07.2025
UBND tỉnh thành lập Ban Chỉ đạo xử lý vướng mắc công tác bồi thường, hỗ trợ, tái định cư trên toàn địa bàn, gỡ điểm nghẽn cản trở tiến độ dự án trọng điểm.
17.07.2025
Các ngành chức năng và địa phương liên quan đang nỗ lực để triển khai 2 dự án khu đô thị trên địa bàn tỉnh Khánh Hòa gồm: Dự án Khu đô thị mới cao cấp Cổ Mã, xã Tu Bông và Khu đô thị hỗn hợp Nha Trang để kịp khởi công vào giữa tháng 8.
11.07.2025
Thị trường bất động sản Nha Trang đang chứng kiến sự dịch chuyển mạnh mẽ. Những khu đô thị đơn thuần, dự án nghỉ dưỡng truyền thống dần nhường chỗ cho mô hình đô thị nghỉ dưỡng đa chức năng – nơi giao thoa giữa an cư, đầu tư và tận hưởng, đích ngắm mới của cả nhà đầu tư lẫn những cư dân tìm kiếm chuẩn sống khác biệt.
11.07.2025

Typical projects
50-70 million/m2
50-70 million/m2
48 triệu/ m2
50-70 million/m2
50-70 million/m2